Written by Squadron Energy |

The project team have been working hard after the break and have successfully completed installation of 72 wind turbines at Clarke Creek Wind Farm. Having almost reached the three-quarter milestone, we are on track to complete the erection of all 100 turbines by June 2025.

Read more in the latest project update.

Share

Other Articles