Construction will now officially commence on Uungula Wind Farm, as we near the completion of the Twelve Mile Road upgrade.
From Monday 31 March 2025, we will start initial work activities, including:
- Earthworks
- Vegetation clearing
- Fencing
- Surveying
- Internal access roads
- Site establishment
- Erosion and sediment control
The work will take place during usual construction hours, from 6am to 7pm on weekdays, and from 8am to 1pm on Saturdays. There will be no work at night, on Sundays, or on public holidays.
As the work progresses, we will provide updates via the project newsletter, website, and Facebook page.
If you have any questions, comments, or would like to request an in-person meeting, please reach out to the Uungula Wind Farm Community Relations Advisor on 0488 820 191.