Oversize overmass (OSOM) movements to the Clarke Creek Wind Farm project site are continuing, including ongoing transportation of turbine components and ancillary electrical components.

The OSOM deliveries take place overnight with police escorts in place where required.

This includes two additional upcoming transformer deliveries that ODLS are undertaking to the Clarke Creek Wind Farm site with the details of those movements listed below.

The first movement will depart Gladstone Port on Tuesday 4 June at 11pm arriving at site at Clarke Creek Wind Farm on Wednesday 5 June at 10am.

Tuesday 4 June

Depart Gladstone Port 2300hrs

Hanson Rd 2330hrs

Wednesday 5 June

Dawson Hwy, Gladstone 0001hrs

Bruce Hwy, Calliope 0030hrs

Marmor 0200hrs

Albert St, Rockhampton 0315hrs

Twelve Mile Creek 0400hrs

Connors Rest Area, Yaamba 0430hrs

Depart: Marlborough South Roadhouse 0700hrs

Arrive: Clarke Creek Wind Farm 1000hrs

The second movement will depart Gladstone Port on Sunday 9 June at 11pm arriving at site on Monday 10 June at 10am.

Sunday 9 June

Start: Exit from Gladstone Port 2300hrs

Hanson Rd 2330hrs

Monday 10 June

Dawson Hwy, Gladstone 0001hrs

Bruce Hwy, Calliope 0030hrs

Marmor 0200hrs

Albert St, Rockhampton 0315hrs

Twelve Mile Creek 0400hrs

Connors Rest Area, Yaamba 0430hrs

Depart: Marlborough South Roadhouse 0700hrs

Arrive: Clarke Creek Wind Farm 1000hrs

Should you have any queries about the project, please get in touch by email clarkecreek@squadronenergy.com or phone 0483 915 303.