Written by Squadron Energy |

On-site work is set to resume at Clarke Creek Wind Farm next week following a full project management review as part of the handover from Windlab to Squadron Energy, which finalises on 30 June.

Activities will ramp up during July in accordance with approved construction plans while the remainder of our project review and re-set is completed.

Trials of oversize overmass (OSOM) deliveries will continue upon reopening of the site to meet the requirements of final transport permits. The community will be informed as updates become available.

Once all approvals are in place, the OSOM transportation will take place overnight with police escorts, running up to six nights per week between 22:30 and 07:00, with later starts on Saturday evenings.

The delivery program is expected to run for around 15 months. Further information will be available soon.

Clarke Creek Wind Farm Stage 1 consists of 100 turbines with a total capacity of 450MW. The project is located 150km northwest of Rockhampton and 150km south of Mackay.