Spicers Creek, NSW

Spicers Creek Battery is a proposed battery storage facility within the Spicers Creek Wind Farm development, west of Gulgong and north east of Wellington, in the Central-West Orana Renewable Energy Zone. The size of the battery facility proposed is up to 400 MW capacity and up to 1,800 MWh storage capacity.

Key Project Info

Battery size and duration

Up to 400 MW capacity / 4.5 hour duration

Planning

The Project is in the Submissions Report phase

Project Timeline

Step 1/13

Project identification and site selection

Identification and site selection is based on an analysis of opportunities and constraints. Our team then begins community consultation.

Current Stage
DSCF1273

Step 2/13

Project feasibility and community engagement

Site-specific investigations are undertaken to assess the impacts and opportunities of the project and feedback is sought from the local community.

Current Stage
160m Mast

Step 3/13

Development Application and Environmental Impact Statement

A Development Application is made and an EIS prepared which involves a wide range of studies to address stakeholder feedback received to date and to consider the potential environmental and social impacts of the project.

Current Stage
Pexels pixabay 357514

Step 4/13

Public exhibition and Submissions Report

The EIS is placed on public exhibition through the NSW Department of Planning, Housing and Infrastructure. Interested members of the public are invited to have their say during the exhibition period by way of formal submissions. A Submissions Report is then prepared, which aims to respond to the submissions received.

Current Stage
IMG 80711

Step 5/13

Assessment and development consent

The project documents are assessed by the relevant government authorities. If determined, Development Consent is granted alongside a range of conditions specific to the project.

Current Stage
SQE Office 12 C

Step 6/13

Post approval, contracting and financing

A lead contractor(s) to build the project is appointed and all pre-construction approvals and consents are finalised. During this phase, the lead contractor(s) is provided with a list of local businesses that have registered their interest and capabilities through the project website.

Current Stage
SQE Office 3 C

Step 7/13

Procurement

During this phase our lead contractor(s) engages contractors and suppliers to undertake the scope of the works. Orders are then placed for major components.

Current Stage
I Stock 479431970 TL

Step 8/13

Early works and design

Initial site activities start. Off-site detailed design commences in parallel.

Current Stage
BWF 02 IMG Early work 191016 3

Step 9/13

Construction - civil works

During this phase of construction, the majority of the civil works takes place. The community is kept informed about temporary impacts during the construction phase.

Current Stage
Step 9

Step 10/13

Construction - mechanical and electrical completion

During this phase, the major equipment packages are delivered to site. Electrical cabling, buildings and amenities are then installed and major equipment connections are made to complete construction.

Current Stage
CRWF 02 IMG Site office 201125 JOW 5 TL

Step 11/13

Commissioning & handover

Electricity and other external service connections are completed and then equipment undergoes performance testing. During this stage, the project will come to life with equipment starting up for short periods of time, until the commissioning team is satisfied with the performance and operational safety. Operators will be trained during commissioning before commencing operations.

Current Stage
20231113 Bango Wind Farm 123

Step 12/13

Operations

The project is operated in accordance with relevant approval conditions and management plans. Compliance with conditions of approval and management plans is monitored as required throughout the life of the project.

Current Stage
SWF 03 Sapphire Wind Farm landscape 230724 12

Step 13/13

Decommissioning

At the end of the project’s useful life, the asset and electrical equipment will be either replaced or the project will be decommissioned. The site will then be returned to its original use or re-purposed for other development.

Current Stage
20231113 i Phone Bango Wind Farm 72

Central-West Orana Renewable Energy Zone

The NSW Government has set out a plan to deliver a number of Renewable Energy Zones (REZ) within the State. The first of these areas is in the Central-West Orana region around Dubbo and Wellington.

A REZ involves the coordinated development of new grid infrastructure in energy rich areas to connect multiple renewable energy generators (such as solar and wind farms) in the same location.

The designation of a REZs is intended to result in the development of additional capacity for renewable electricity generation, producing low-cost power for NSW homeowners and business, driving down carbon emissions within the electricity generation sector, and importantly, driving up job growth and employment opportunities through enabling significant investment into the regions.

For more information on the Central West-Orana REZ, including an indicative location, visit https://www.energyco.nsw.gov.au/renewable-energy-zones

Community

The wellbeing of the community is a core component of our work. Our approach to engaging with the local community is both genuine and lasting. We own our projects from development right through to operations. This gives us unrivalled experience through the entire project life and provides us with a deep-founded respect for people, communities and the environment.

Our team work respectfully with the communities in which we work, are sensitive to environmental and cultural values and aims to make a positive contribution to the regions in which we operate.

We welcome your contact and feedback should you have any questions or concerns about the proposed Spicers Creek Battery.

CWP Sapphire Wind Farm JOW 201112 7532  

CWP Sapphire Wind Farm JOW 201112 7400  

About Squadron Energy

Squadron Energy is Australia’s leading renewable energy company that develops, operates and owns renewable energy assets in Australia. We are 100% Australian owned and have 1.1 gigawatts (GW) of renewable energy in operation and 900MW under construction. With proven experience and expertise across the project lifecycle, we work with local communities and our customers to lead the transition to Australia’s clean energy future.

Contact

Project Manager

Trish McDonald

Email: spicerscreekwind@squadronenergy.com

Tel: 1800 095 754

Mailing Address

PO Box 1708, Newcastle, NSW 2300

Newsletter

Receive the latest Spicers Creek Battery project updates straight to your inbox