Written by Squadron Energy |

Major work activities are progressing onsite at Clarke Creek Wind Farm and we have now completed 75 per cent of our oversize overmass (OSOM) deliveries to the project site. The last shipment of components has also arrived at Gladstone Port.

The OSOM movements are continuing and include ongoing transportation of turbine components and ancillary electrical components.

The OSOM deliveries take place overnight with police escorts in place where required.

The loads depart Gladstone Port between 11.30pm and 1am, arriving at site between 5am and 7am.

Due to the Christmas travel restrictions, there will be no deliveries from Thursday 19 December 2024 to midnight Thursday 2 January 2025

These times may change if unforeseen circumstances arise.

For up-to-date information about transportation movements, residents and road users can:

  • sign up for SMS messages by providing your mobile number to clarkecreek1@squadronenergy.com
  • look out for the multiple electronic signage boards in use along the route.

The following routes are used under current plans:

  • Gladstone Port Access Road
  • Gladstone–Mt Larcom Road (including Hanson Road)
  • Dawson Highway (Gladstone–Calliope)
  • Bruce Highway (Calliope–Rockhampton–Marlborough)
  • Marlborough–Sarina Road
  • various local government roads in the Gladstone area.

Should you have any queries about the project, please get in touch by email clarkecreek1@squadronenergy.com or phone 0483 915 303.