Upgrade work on Twelve Mile Road to resume

Work is continuing on the Twelve Mile Road upgrade, despite weather and poor ground condition impacts. To reduce delays, we are planning to mobilise Transgrid to the Uungula Wind Farm site in the middle of February 2025. Final work on Twelve Mile Road will be done in parallel with Transgrid preparing for work. We are […]
Frequently asked questions: wind energy in Australia

Curious about wind energy and how wind farms work? Here are the answers to some of our most frequently asked questions at Squadron Energy.
Spicers Creek Wind Farm community newsletter – December 2024

In a huge project milestone, NSW State approval was received from the Independent Planning Commission (IPC) on 31 October 2024. The Commissioners visited the site in August, followed by the Public Meeting held at the Dunedoo Jubilee Memorial Hall. The project is now being assessed for Commonwealth approval by the Department of Climate Change, Energy, […]
Squadron Energy helps more than 1,200 helicopter rescues in Northern NSW

Squadron Energy CEO Rob Wheals said the team were proud to support this vital service for a second year. “We know how important this chopper service is and are proud to be continuing our support to help it deliver critical emergency medical services, supporting 1.5 million people across Northern NSW,” Mr Wheals said. “We are […]
Jeremiah Wind Farm project update – December 2024

This year, we were excited to partner with so many local groups and organisations between Jugiong and Tumut to support the delivery of a range of community events, programs, and infrastructure. Read more in the latest project update.
Boorolong Wind Farm community newsletter – December 2024

Since our last edition we have met with many of our stakeholders to gather and provide information, understand concerns and receive feedback on the project. This is an ongoing activity – we always welcome your feedback. Read more in the latest community newsletter.
Uungula Wind Farm project update – December 2024

Since our last update in November, we have been making great progress. Service relocations (underground pipes and cables) for the Goolma Road and Twelve Mile Road upgrade are now on track for completion in early 2025. Read more in the latest project update.
Conargo Wind Farm community newsletter – December 2024

In March 2024, the project team held a community information session in Conargo. Since then, we have been engaging with individual community members, as well as local organisations including the Rural Fire Service (RFS) and Council’s economic development team. Read more in the latest community newsletter.
Koorakee Energy Park community newsletter – December 2024

The project entered the NSW planning system in May when the Secretary’s Environmental Assessment Requirements (SEARs) were requested. A Scoping Report, detailing key information and identifying environmental and social considerations for the project, was submitted. Read more in the latest community newsletter.
Gol Gol Renewable Energy Projects community newsletter – December 2024

The project entered the NSW planning system in May when the Secretary’s Environmental Assessment Requirements (SEARs) were requested. A Scoping Report, detailing key information and identifying environmental and social considerations for the project, was submitted. The Scoping Report and SEARs are both available under the Documents tab on the project website. Read more in the latest community […]