OSOM delivery schedule 3 May to 24 May 2026

Oversize overmass deliveries to Uungula Wind Farm are now underway. Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on. Refer to the schedule for delivery […]
OSOM delivery schedule 27 April to 17 May 2026

Oversize overmass deliveries to Uungula Wind Farm are due to start in late April. Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on. Refer to […]
Spicers Creek Wind Farm community newsletter – April 2026

As we continue work on secondary approvals, contracting and project financing in readiness for wind farm construction, we have several project updates to share with you. Read more in the latest community newsletter.
Conargo Wind Farm community newsletter – April 2026

The Conargo Wind Farm project team continues to refine the project layout, informed by ongoing technical and environmental assessments such as flood and hydrology modelling and biodiversity surveys. Read more in the latest community newsletter.
Ballyrogan Wind Farm community newsletter – March 2026

Welcome to the first Ballyrogan Wind Farm community newsletter for 2026 which provides updates on project progress and upcoming activities for the wider community. Read more in the latest community newsletter.
Moreton Hill Wind Farm community newsletter – March 2026

Since our last newsletter in December, we have been finalising the planning permit application. This has included ongoing work with Wadawurrung Traditional Owners Aboriginal Corporation to progress the Cultural Heritage Management Plan.
Clarke Creek Wind Farm Stage 2 project update – January 2026

The Clarke Creek Wind Farm – Stage 2 team are finalising the project layout for the change application to the existing State Approval. As part of this work, we are assessing impacts on traffic, transport, noise, visual, social and economic factors, and opportunities resulting from the project. Read more in the latest project update.
Bookham Wind Farm project update – December 2025

As we approach the end of the year, the Bookham Wind Farm team at Squadron Energy would like to extend our thanks for your continued interest and involvement in the project. Read more in the latest project update.
Moreton Hill Wind Farm community newsletter – December 2025

As 2025 draws to a close, we are delighted to share the final Moreton Hill Wind Farm newsletter for this year. Reflecting on the past 12 months, it’s been a year of significant progress and collaboration. Our team has been pleased to work alongside our host landowners, neighbours, and community members, as well as local, […]
Clarke Creek Wind Farm community newsletter – December 2025

The Clarke Creek Wind Farm project team has successfully completed the installation of all 100 turbines, marking a major milestone for the project. Thank you to our project team and all our partners involved.