Clarke Creek Wind Farm oversize overmass movements continue
As part of the Clarke Creek Wind Farm project’s next phase, oversize overmass (OSOM) movements will continue to the project site, including ongoing transportation of

As part of the Clarke Creek Wind Farm project’s next phase, oversize overmass (OSOM) movements will continue to the project site, including ongoing transportation of

Clarke Creek Wind Farm oversize overmass (OSOM) trial runs have been completed and equipment deliveries from Gladstone Port to the project site are continuing as

When a mayor is not seeing local benefits from a renewables project, there is something wrong. The concerns voiced by Goondiwindi Mayor Lawrence Springborg recently

Squadron Energy is committed to the protection and preservation of the environment. We have a certified Environmental Management System, an experienced team of environmental staff

Clarke Creek Wind Farm Stage 1 is under construction, 150 km north-west of Rockhampton and 150km south of Mackay on the land of the Barada

We are getting on with the critical delivery of new renewable generation. As confirmed in the latest GenCost report from the CSIRO and the Australian Energy Market

On-site work is set to resume at Clarke Creek Wind Farm next week following a full project management review as part of the handover from

The first 76m-long wind turbine blade and a 100-tonne tower component have been successfully delivered to Clarke Creek Wind Farm during a trial run of Over Size

Clarke Creek Wind Farm Stage 1 is a renewable energy project currently under construction, 50km west of Marlborough QLD. It will see 100 wind turbines

Wind energy has come a long way in Australia since operations began at the first commercial wind farm in 1987. In the past decade, wind