News Uungula Wind Farm

Australia’s leading renewable energy companies welcome investigations into renewable energy generation in Outback NSW

Western NSW Industry Group, which is comprised of renewable energy companies such as Squadron Energy, Iberdrola Australia and Tilt Renewables, welcome investigations into renewable energy generation in Far Northwest and Western NSW.
We are supportive of the current energy roadmap. Consistency of government energy policy is critical if companies are to continue to invest with confidence in the energy transition.

Read More »

OSOM delivery schedule 21 June to 12 July 2026

Oversize overmass (OSOM) deliveries to Uungula Wind Farm are now underway.

Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on.

Read More »

Pre-installation begins for Uungula Wind Farm turbines

Wind turbine pre-installation is underway at Squadron Energy’s Uungula Wind Farm, marking the next stage of construction for the project.
Pre-installation, which involves using cranes to install the lower sections of the tower, began at the project site earlier this month.

Read More »

Regional artists design upcoming Squadron Energy activity book

Local Dubbo-based artist Annette Ferguson is behind the cover of this year’s Squadron Energy activity book.
The upcoming children’s book features engaging puzzles, captivating artwork and educational content.
Annette, who is visually impaired, drew on her upbringing in the country and her connection to the land as inspiration for her artwork.

Read More »

OSOM delivery schedule 7 June to 28 June 2026

Oversize overmass (OSOM) deliveries to Uungula Wind Farm are now underway. Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on.

Read More »

OSOM delivery schedule 24 May to 14 June 2026

Oversize overmass (OSOM) deliveries to Uungula Wind Farm are now underway.

Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on.

Read More »

Western Sydney manufacturing helping power NSW energy transition

Australian manufacturers a playing a key role in the construction of Squadron Energy’s Uungula Wind Farm – the only wind farm under construction in New South Wales.
Precision Oxycut, a steel-cutting company in Western Sydney, fabricates steel plates for the wind farm’s anchor cages, which sit at the base of each turbine and ensure structural stability.
These plates are made using steel from fellow local manufacturer, Bluescope.

Read More »

OSOM delivery schedule 17 May to 7 June 2026

Oversize overmass deliveries to Uungula Wind Farm are now underway. Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on.

Read More »

Uungula Wind Farm supports next generation of cricketers in Wellington 

Squadron Energy’s Uungula Wind Farm sponsored the Wellington Junior Cricket Club for the 2025/2026 cricketing season, which led to the purchase of brand-new playing shirts and caps for players. It also provided awards for the club’s end-of-season presentation last month.
The club recognised Squadron Energy and other sponsors for their ongoing support.

Read More »