Commencement of construction
Construction will now officially commence on Uungula Wind Farm, as we near the completion of the Twelve Mile Road upgrade. From Monday 31 March 2025,

Construction will now officially commence on Uungula Wind Farm, as we near the completion of the Twelve Mile Road upgrade. From Monday 31 March 2025,

Work is continuing on the Twelve Mile Road upgrade, despite weather and poor ground condition impacts. To reduce delays, we are planning to mobilise Transgrid

The next stage of the Uungula Wind Farm road upgrade work is starting on Ilgingery Road, Wuuluman. A key part of planning for the widening

Work on Twelve Mile Road currently includes: To protect flora and fauna during this work, we have installed environmental controls. All work is required to

From Wednesday 19 June 2024, Twelve Mile Road causeway around 7km east of Goolma and Twelve Mile roads intersection will be reduced to one lane

Construction activity on Twelve Mile Road is currently focused on preparation works including the use of heavy machinery, in preparation for road re-sheeting. Ongoing works

Vegetation clearing and pruning has started along Twelve Mile Road in preparation for the widening and re-sheeting of the road, making it safer for all

Squadron Energy understands that there have been concerns publicly expressed regarding the transport of Over Size Over Mass (OSOM) equipment on Twelve Mile Road at

From Monday 20 May 2024, Twelve Mile Road will have sections of bitumen removed for road upgrade works. This will mean that there will be a

A section of Twelve Mile Road will now have a speed limit of 60km/h due to the road upgrade. The speed restrictions will start from