
Dragons on the trail to promote health and resilience to students for the Central West Blitz
The St George Illawarra Dragons have wrapped another successful Community Blitz after visiting schools and hosting workshops throughout the state’s
Our projects
Wind turbines
Commercial operations
Maximum capacity
Annual output
PPA partners
75k
Homes powered
266k
Tonnes of emissions avoided
240
Direct jobs created
$21m
Regional investment

The St George Illawarra Dragons have wrapped another successful Community Blitz after visiting schools and hosting workshops throughout the state’s

The Dragons will this week again team up with Squadron Energy to deliver the club’s Best You Can Be Blitz

A myriad of significant community programs and local initiatives supported by Squadron Energy have been featured in the latest Best Practice

Three months after its grand opening, the Windeyer playground has been a hit with families throughout the local community. The

The restoration of Turondale’s aging tennis court will start soon thanks to $45,000 of funding from Bathurst Regional Council’s Voluntary

Squadron Energy welcomes progress on the implementation of the Federal Government’s Developer Rating Scheme, which aims to promote best practice engagement among

Curious about wind energy and how wind farms work? Here are the answers to some of our most frequently asked questions at

It has been a busy year for Squadron Energy. Read about our progress this year in our Year in review.

The latest Electricity Statement of Opportunities (ESOO) from AEMO is a welcomed confirmation that renewable energy generation is on track to replace exiting coal

Squadron Energy CEO Rob Wheals said: “The 2024 Integrated System Plan (ISP) reaffirms the comprehensive planning and implementation done to date on

The local community came together on Wednesday 19 June to officially open Squadron Energy’s new office in Wellington NSW, further

Squadron Energy, Australia’s leading renewable energy company, and Dubbo Regional Council plan to deliver water security to the region through

Are you interested in learning more about investing in renewable energy? DomaCom and Squadron Energy are hosting three online community

The three-day program included school visits and clinics run by NRL and NRLW Dragons players and ambassadors in Goolma, Wellington,

Squadron Energy and DomaCom invite you to attend one of our Community Information Sessions to learn more about the Squadron

An exciting preview of the 2024 season, the 2024 NRL Trial match against the Wests Tigers marked the Dragons seventh

Footy fans from the Central West region are invited to Lawson Park, Mudgee on Saturday 24 February for an exciting

As we continue on our mission to lead Australia’s clean energy transition, we look back on some of our key

Driving past numerous wind farms while travelling between Broken Hill and Adelaide sparked something for Kacee Milnes. The 34 year-old

Three years after translocating wattle from Crudine Ridge Wind Farm (CRWF), the plants are still healthy in their new habitat.

We are getting on with the critical delivery of new renewable generation. As confirmed in the latest GenCost report from the CSIRO

Wind energy has come a long way in Australia since operations began at the first commercial wind farm in 1987.

CWP Renewables has joined forces with Squadron Energy to become the Australian leader in renewable energy. CWP Renewables was acquired

Growth has been our theme for 2022. We completed construction on two wind farms, launched two new projects and delivered

Hosting a renewable energy project doesn’t just contribute to cleaner energy. It provides an additional income stream for the host,

Renewable energy developer and operator CWP Renewables is again calling on community groups and charities to apply for support in

As we enter the final quarter of 2022, we also mark National Safe Work Month – with SafeWork Australia this year encouraging

Renewable energy company CWP Renewables opened its gates last week with schools and community members getting up close to wind

The transition to renewable energy has well and truly been in the spotlight to date this year. Not only have

Central West locals looking to build in-demand work health and safety skills can now benefit from a new partnership between

As a leading renewable energy developer and operator, we have an asset management portfolio of more than 750 MW and

Clean energy developer and operator CWP Renewables (CWPR) has launched its inaugural Reconciliation Action Plan (RAP), taking an important step

Food and beverage manufacturer Nestlé Australia has made the switch to 100% renewable electricity, entering into a power purchase agreement

Renewable energy developer and operator CWP Renewables is calling on community groups and charities to apply for sponsorship in a

We have had a chilly start to winter at Crudine Ridge and our commissioning and operations teams battled the elements
"We had a lot of fun and we learnt lots about turbines. The turbines were huge and when the blades were spinning above us it made me relaxed. It was really cool when there was a blade on the ground to see what it looked like closer to us instead of it being up in the air."
Hargraves School Student
Step 1
Project identification and site selection
Identification and site selection is based on an analysis of opportunities and constraints including (but not limited to): distance to the electricity grid, wind resource and population density of the surrounding community. Our team then undertake a number of site visits and consultation with landowners in the area.
Project identification and site selection
Step 2
Project feasibility and community engagement
Site-specific investigations are undertaken to assess the impacts and opportunities of the project and feedback is sought from the local community.
Project feasibility and community engagement
Step 3
Development application and environmental impact statement
A Development Application is made and an EIS prepared which involves a wide range of studies to address stakeholder feedback received to date and to consider the potential environmental and social impacts of the project.
Development application and environmental impact statement
Step 4
Public exhibition and Submissions Report
The EIS is placed on public exhibition through the NSW Department of Planning, Housing and Infrastructure. Interested members of the public are invited to have their say during the exhibition period by way of formal submissions. A Submissions Report is then prepared, which aims to respond to the submissions received.
Public exhibition and Submissions Report
Step 5
Assessment and development consent
The project documents are assessed by the relevant government authorities. If determined, Development Consent is granted alongside a range of conditions specific to the project.
Assessment and development consent
Step 6
Post approval, contracting and financing
A lead contractor(s) to build the project is appointed and all pre-construction approvals and consents are finalised. During this phase, the lead contractor(s) is provided with a list of local businesses that have registered their interest and capabilities through the project website.
Post approval, contracting and financing
Step 7
Procurement
During this phase our lead contractor(s) seek tenders and engage contractors and suppliers to undertake the scope of the works. Orders are then placed for major components such as the wind turbines.
Procurement
Step 8
Early works and design
Initial site activities commence, such as minor clearing and provision of access roads along with establishing a site construction compound. Off-site detailed design works commences in parallel.
Early works and design
Step 9
Major civil works
During this phase of the construction the bulk of the civil works takes place. This includes the construction of new internal access roads, excavation and construction of the turbine foundations, installation of the internal electrical reticulation system, construction of the high voltage substation and main transmission line network.
Major civil works
Step 10
Wind turbine erection
This is where the visual aspect of the wind farm starts to emerge, with large cranes lifting the tower sections, nacelle, hub and blades into place.
Wind turbine erection
Step 11
Commissioning
In order to export power to the grid, each turbine is required to undergo several performance tests. It is during this stage that you will start to see turbines spinning and ultimately the whole of the wind farm complete.
Commissioning
Step 12
Operations
The project is operating in accordance with relevant approval conditions and management plans. Compliance with conditions of approval and management plans is monitored as required throughout the life of the project.
Operations
Step 13
Decommissioning
The design life of the wind turbines will be at least 30 years. At the end of their useful life, the wind turbines and electrical equipment will be either replaced and the wind farm repowered, or the project will be decommissioned, and the site returned to its original use at the expense of the project.
Decommissioning
St George Illawarra Dragons, in partnership with Squadron Energy, delivers an impactful Community Blitz in the state's Central West yearly.
The program, the Best You Can Be Blitz, sees the players and club community staff speak at schools and host workshops for students across the region.
In the latest program, NRLW stars Keele Browne and Ella Koste visited eight schools in Ilford, Kandos, Dunedoo, Mendooran and Gilgandra over three days.
A touch footy clinic was also held in Dunedoo along with a Win the Morning event with the Gilgandra Shire Breakfast Club.
Workshops hosted by the club provide advice on staying active, learning how to practice tolerance, respect and inclusiveness, the importance of good sleep, screen time management, hydration, nutrition, and the importance of taking care of the environment.
Squadron Energy's Crudine Ridge Wind Farm supported the creation of a playground in Windeyer for residents.
The playground, which was unveiled to the public by Mid-Western Regional Council in early August, has been highly popular with local families and is used frequently.
Features of the park include swings, a slippery dip, a ladder and ropes for climbing.
On its opening day, Squadron Energy also helped supply food for attendees.
An aging tennis court will be completely restored for the small community of Turondale after backing from Squadron Energy.
The funds for the upgrade have been provided by Squadron Energy's Crudine Ridge Wind Farm via Bathurst Regional Council's Voluntary Planning Agreement.
The restoration for the court includes a new court slab, upgraded net and perimeter fencing.
A community benefit fund has been established in the form of a Voluntary Planning Agreement (VPA) with the Mid-western Regional and Bathurst Regional Council.
Crudine Ridge Wind Farm will contribute $4.8m over the life of the project. The funds will be split between the two councils according to the number of the turbines installed within each local government area.
The funds will be allocated by each council to enhance community projects and initiatives in accordance with their community plan.
VPA documents are provided below.
The Crudine Ridge community sponsorship program provides funds or in-kind support to community organisations and events in the Mid-Western Shire and Bathurst Regional Council areas.
The program supports initiatives that strengthen our local community, through programs that make a positive and lasting contribution
Priority areas for the program include:
• Education and training initiatives
• Community development programs
• Health and wellbeing
• Environmental initiatives
The purpose of a community consultative committee (CCC) is to provide a forum for open discussion.
It is a space for us to speak with representatives from the community, the council and other stakeholders about specific matters relating to the project.
The CCC follows the NSW Department of Planning, Industry and Environment’s Community Consultative Committee Guidelines for State Significant Projects. Meeting minutes are provided below.
If you would like to get in touch with your local CCC member,
please contact the Independent Chairperson:
David Johnson:
johnson08@iinet.net.au
Download
Download
Download
Download
Download
App 04 Greenhouse Gas Savings Tool
Download
Download
App 06 Stakeholder Responses Part B
Download
Download
Download
Download
Download
App 12 Ecological Assessment - A
Download
App 12 Ecological Assessment - B
Download
App 12 Ecological Assessment - C
Download
Download
Download
Download
Download
App 17 Guidelines for Landing Areas
Download
App 19 Communications Responses
Download
App 20 Bush Fire Risk Assessment
Download
Download
Download
App 23 Department of Lands Response
Download
Download
Download
Landscape Visual Impact Assessment A
Download
Landscape Visual Impact Assessment B
Download
Download
State Significant Development MOD 3
Download
Environmental Management Strategy
Download
Download
Download
Download
Biodiversity Stewardship Agreement
Download
EPBC Annual Compliance Report 2025
Download
EPBC Annual Compliance Report 2024
Download
EPBC Annual Compliance Report 2023
Download
EPBC Annual Compliance Report 2022
Download
EPBC Annual Compliance Report 2021
Download
EPBC Annual Compliance Report 2020
Download
Independent Environmental Audit 2025
Download
Independent Environmental Audit 2022
Download
Independent Environmental Audit 2020
Download
Independent Environmental Audit 2019
Download
BBAMP Monitoring Report Year One
Download
BBAMP Monitoring Report Year Two
Download
BBAMP Monitoring Report Year Three
Download
Operational Noise Compliance Testing
Download
APR Vegetation Clearing Report
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download