News UWF construction updates

OSOM delivery schedule 21 June to 12 July 2026

Oversize overmass (OSOM) deliveries to Uungula Wind Farm are now underway.

Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on.

Read More »

Pre-installation begins for Uungula Wind Farm turbines

Wind turbine pre-installation is underway at Squadron Energy’s Uungula Wind Farm, marking the next stage of construction for the project.
Pre-installation, which involves using cranes to install the lower sections of the tower, began at the project site earlier this month.

Read More »

OSOM delivery schedule 7 June to 28 June 2026

Oversize overmass (OSOM) deliveries to Uungula Wind Farm are now underway. Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on.

Read More »

OSOM delivery schedule 24 May to 14 June 2026

Oversize overmass (OSOM) deliveries to Uungula Wind Farm are now underway.

Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on.

Read More »

Western Sydney manufacturing helping power NSW energy transition

Australian manufacturers a playing a key role in the construction of Squadron Energy’s Uungula Wind Farm – the only wind farm under construction in New South Wales.
Precision Oxycut, a steel-cutting company in Western Sydney, fabricates steel plates for the wind farm’s anchor cages, which sit at the base of each turbine and ensure structural stability.
These plates are made using steel from fellow local manufacturer, Bluescope.

Read More »

OSOM delivery schedule 17 May to 7 June 2026

Oversize overmass deliveries to Uungula Wind Farm are now underway. Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on.

Read More »