Upgrade of Goolma Road and Twelve Mile Road intersection
On Monday 28 July 2025, work will start on the upgrade of the new Goolma Road and Twelve Mile Road intersection, weather and site conditions

On Monday 28 July 2025, work will start on the upgrade of the new Goolma Road and Twelve Mile Road intersection, weather and site conditions

What work are we doing? Squadron Energy’s Uungula Wind Farm is extending construction hours from Wednesday 18 June 2025 to Tuesday 30 June 2026, in

Twelve Mile Road has returned to its original speed limit of 100km/h following the completion of road upgrades. This updated limit takes effect today (Monday,

Local communities in the Central West now have access to a safer and better road, with the completion of the Twelve Mile Road upgrade near

Construction will now officially commence on Uungula Wind Farm, as we near the completion of the Twelve Mile Road upgrade. From Monday 31 March 2025,

Work is continuing on the Twelve Mile Road upgrade, despite weather and poor ground condition impacts. To reduce delays, we are planning to mobilise Transgrid

The next stage of the Uungula Wind Farm road upgrade work is starting on Ilgingery Road, Wuuluman. A key part of planning for the widening

Work on Twelve Mile Road currently includes: To protect flora and fauna during this work, we have installed environmental controls. All work is required to

From Wednesday 19 June 2024, Twelve Mile Road causeway around 7km east of Goolma and Twelve Mile roads intersection will be reduced to one lane

Construction activity on Twelve Mile Road is currently focused on preparation works including the use of heavy machinery, in preparation for road re-sheeting. Ongoing works