Uungula Wind Farm community newsletter – July 2026

Share

As we reach the halfway point of the year, it’s a great opportunity to reflect on the progress we’ve made at Uungula Wind Farm and what is coming next. We have reached some important milestones including the start of oversize overmass (OSOM) deliveries to site and the completion of the first nine pre-installations of tower sections, with blade deliveries to start in the next few weeks.