
Squadron Energy shows community initiative through Best Practice Charter Report
A myriad of significant community programs and local initiatives supported by Squadron Energy have been featured in the latest Best Practice
Our projects
Planning
Local government area
410k
Expected homes powered
300k
Expected tonnes of emissions avoided
738MW
Expected capacity

A myriad of significant community programs and local initiatives supported by Squadron Energy have been featured in the latest Best Practice

The proposed Saddletop Wind Farm is located on Wiradjuri Country, around 30km north east of Tumut, NSW. The proposed wind

Squadron Energy is inviting the community to provide feedback on a proposed wind farm near Adjungbilly, on Wiradjuri Country, around

Squadron Energy welcomes progress on the implementation of the Federal Government’s Developer Rating Scheme, which aims to promote best practice engagement among

Curious about wind energy and how wind farms work? Here are the answers to some of our most frequently asked questions at

It has been a busy year for Squadron Energy. Read about our progress this year in our Year in review.

The latest Electricity Statement of Opportunities (ESOO) from AEMO is a welcomed confirmation that renewable energy generation is on track to replace exiting coal

As we continue on our mission to lead Australia’s clean energy transition, we look back on some of our key
Step 1
Project identification and site selection
Identification and site selection is based on an analysis of opportunities and constraints including (but not limited to): distance to the electricity grid, wind resource and population density of the surrounding community. Our team then undertake a number of site visits and consultation with landowners in the area.
Project identification and site selection
Step 2
Project feasibility and community engagement
Site-specific investigations are undertaken to assess the impacts and opportunities of the project and feedback is sought from the local community.
Project feasibility and community engagement
Step 3
Development Application and Environmental Impact Statement
A Development Application is made and an EIS prepared which involves a wide range of studies to address stakeholder feedback received to date and to consider the potential environmental and social impacts of the project.
Development Application and Environmental Impact Statement
Step 4
Public exhibition and submissions report
The EIS is placed on public exhibition through the NSW Department of Planning, Housing and Infrastructure. Interested members of the public are invited to have their say during the exhibition period by way of formal submissions. A Submissions Report is then prepared, which aims to respond to the submissions received.
Public exhibition and submissions report
Step 5
Assessment and development consent
The project documents are assessed by the relevant government authorities. If determined, Development Consent is granted alongside a range of conditions specific to the project.
Assessment and development consent
Step 6
Post approval, contracting and financing
A lead contractor(s) to build the project is appointed and all pre-construction approvals and consents are finalised. During this phase, the lead contractor(s) is provided with a list of local businesses that have registered their interest and capabilities through the project website.
Post approval, contracting and financing
Step 7
Procurement
During this phase our lead contractor(s) seek tenders and engage contractors and suppliers to undertake the scope of the works. Orders are then placed for major components such as the wind turbines.
Procurement
Step 8
Early works and design
Initial site activities commence, such as minor clearing and provision of access roads along with establishing a site construction compound. Off-site detailed design works commences in parallel.
Early works and design
Step 9
Major civil works
During this phase of the construction the bulk of the civil works takes place. This includes the construction of new internal access roads, excavation and construction of the turbine foundations, installation of the internal electrical reticulation system, construction of the high voltage substation and main transmission line network.
Major civil works
Step 10
Wind turbine erection
This is where the visual aspect of the wind farm starts to emerge, with large cranes lifting the tower sections, nacelle, hub and blades into place.
Wind turbine erection
Step 11
Commissioning
In order to export power to the grid, each turbine is required to undergo several performance tests. It is during this stage that you will start to see turbines spinning and ultimately the whole of the wind farm complete.
Commissioning
Step 12
Operations
The project is operating in accordance with relevant approval conditions and management plans. Compliance with conditions of approval and management plans is monitored as required throughout the life of the project.
Operations
Step 13
Decommissioning
The design life of the wind turbines will be at least 30 years. At the end of their useful life, the wind turbines and electrical equipment will be either replaced and the wind farm repowered, or the project will be decommissioned, and the site returned to its original use at the expense of the project.
Decommissioning
Squadron Energy proudly supports these recent local initiatives:
The wellbeing of the community is a core component of our work. Our approach to engaging with the local community is both genuine and lasting.
We develop, operate, and own our renewable energy projects. This gives us unrivalled experience through the entire project life and provides us with a deep-founded respect for people, communities and the environment in which we operate. We work together with communities on opportunities for our projects to enhance the economic and social development of the region.
We welcome your contact and feedback should you have any questions or concerns about the proposed Saddletop Wind Farm.
We share the benefits of our projects by supporting communities over the long term. We do this through a range of opportunities such as community benefits funds, voluntary planning agreements, community sponsorship and grant initiatives.
We recognise that each community is different, and we aim to tailor benefits at each project and make positive lasting contribution to each region.
Each of our projects has a community sponsorship program, which provides funds or in-kind support to community organisations and events in the local project area.
Key areas for the program include:
• Education and training initiatives
• Community development programs
• Health and wellbeing
• Environmental initiatives
Applications are open for community sponsorship. Please contact us using the details below for more information about Saddletop Wind Farm community sponsorship opportunities. Download and complete the Community Sponsorship Application and forward with any relevant documentation to info@squadronenergy.com.
Alternatively, you can complete and submit the form online via the link below.
Download
May 2025 - Community Newsletter
Download