Causeway upgrade work on Twelve Mile Road

From Wednesday 19 June 2024, Twelve Mile Road causeway around 7km east of Goolma and Twelve Mile roads intersection will be reduced to one lane for causeway upgrade work. Please note speed limit restrictions will be in place during the upgrade work for the safety of workers and all road users.
Construction activities on Twelve Mile Road

Construction activity on Twelve Mile Road is currently focused on preparation works including the use of heavy machinery, in preparation for road re-sheeting. Ongoing works consist of road surveying, drainage upgrades, driveway and fencing construction. Speed limit restrictions with lane closures will be in place during these works. Road users are likely to experience delays. […]
Squadron Energy celebrates World Environment Day

Can you tell us about your background and what led you to pursue a career focused on the environment? For as far as I can remember I have always been fascinated by nature. All through my childhood, I have watched endless hours of David Attenborough’s documentaries, hoping one day I would be lucky enough to […]
Clarke Creek Wind Farm hosts local school students

Students from Clarke Creek Primary School enjoyed a site visit on Friday 31 May, donning hard hats and hi-vis to inspect the construction progress up close. With students from Years 1 and 2 currently exploring important places in their community, the excursion aimed to enhance students’ understanding of renewable energy projects in their region, with […]
Uungula Wind Farm community newsletter – May 2024

Squadron Energy and its main contractors, Nacap and Maas, have started pre-construction activities for Uungula Wind Farm, which is the largest wind farm being built in New South Wales. This involves an upgrade to Twelve Mile Road, including safety upgrades to the Goolma Road intersection, a wider and improved bitumen road surface and upgraded drainage, […]
Vegetation clearing on Twelve Mile Road

Vegetation clearing and pruning has started along Twelve Mile Road in preparation for the widening and re-sheeting of the road, making it safer for all vehicles. All trees are inspected prior to pruning or removal. Squadron Energy has a qualified arborist to provide inspections and advice on tree removal and/or pruning. This includes checking tree […]
Equipment deliveries explained

Squadron Energy understands that there have been concerns publicly expressed regarding the transport of Over Size Over Mass (OSOM) equipment on Twelve Mile Road at the same time as stock trucks are leaving local farms. There will be no OSOM deliveries until late 2025 at the earliest. We recently held a transport workshop in Wellington, […]
Squadron Energy supports University of Wollongong students to compete at Indigenous Nationals

University of Wollongong (UOW) will field not one, but two teams to compete in the Indigenous Nationals at the Wollongong campus from 23-27 June. The Indigenous Nationals is an annual week-long multisport event that unites students from universities across Australia to vie in a range of sports, ultimately determining the champion university team of the […]
Oversize overmass transport update – June 2024

Oversize overmass (OSOM) movements to the Clarke Creek Wind Farm project site are continuing, including ongoing transportation of turbine components and ancillary electrical components. The OSOM deliveries take place overnight with police escorts in place where required. This includes two additional upcoming transformer deliveries that ODLS are undertaking to the Clarke Creek Wind Farm site […]
Dubbo Firming Power Station project update – May 2024

Dubbo Firming Power Station has been approved by the NSW Department of Planning, Housing and Infrastructure and the NSW Independent Planning Commission. This is a major milestone for the project and we are grateful to everyone who provided feedback and engaged with us during the consultation and planning phases. Read more in the latest project update.