OSOM delivery schedule 24 May to 14 June 2026

Oversize overmass (OSOM) deliveries to Uungula Wind Farm are now underway.
Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on.
Upgrade to Mitchell Highway and Goolma Road intersection

Squadron Energy’s Uungula Wind Farm is upgrading the intersection of Mitchell Highway and Goolma Road to improve safety and support oversize overmass deliveries of wind turbine components to the project site. The work will be completed in two stages. Stage 1 on the south side of Goolma Road (carwash side) is underway and is expected […]
Western Sydney manufacturing helping power NSW energy transition

Australian manufacturers a playing a key role in the construction of Squadron Energy’s Uungula Wind Farm – the only wind farm under construction in New South Wales.
Precision Oxycut, a steel-cutting company in Western Sydney, fabricates steel plates for the wind farm’s anchor cages, which sit at the base of each turbine and ensure structural stability.
These plates are made using steel from fellow local manufacturer, Bluescope.
OSOM delivery schedule 17 May to 7 June 2026

Oversize overmass deliveries to Uungula Wind Farm are now underway. Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on.
Uungula Wind Farm supports next generation of cricketers in Wellington

Squadron Energy’s Uungula Wind Farm sponsored the Wellington Junior Cricket Club for the 2025/2026 cricketing season, which led to the purchase of brand-new playing shirts and caps for players. It also provided awards for the club’s end-of-season presentation last month.
The club recognised Squadron Energy and other sponsors for their ongoing support.
OSOM delivery schedule 3 May to 24 May 2026

Oversize overmass deliveries to Uungula Wind Farm are now underway. Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on. Refer to the schedule for delivery […]
First turbine components for Uungula Wind Farm arrive at site

The first wind turbine components have been delivered to Squadron Energy’s Uungula Wind Farm, signalling the start of the next phase of the project.
Oversize overmass (OSOM) deliveries started this week, with components transported from the Port of Newcastle to site.
OSOM delivery schedule 27 April to 17 May 2026

Oversize overmass deliveries to Uungula Wind Farm are due to start in late April. Towers and the machine head will depart Newcastle in early mornings, with departures spaced 30 minutes apart to ensure smooth passage through the city. They may be required to stop at Warkworth and wait for sunrise before moving on. Refer to […]
Doors open at revamped Bellhaven facility for Uungula Wind Farm workers

Bellhaven, the former aged care facility, has opened its doors to workers working on Squadron Energy’s Uungula Wind Farm.
Squadron Energy has the facility turned into a temporary workers accommodation following an extensive refurbishment by local First Nations contractors.
Intersection upgrade improves safety for motorists and progresses Uungula Wind Farm

The upgrade to the Goolma Road and Twelve Mile Road intersection has been completed, creating a widened and improved intersection for communities in the Central West.
Squadron Energy upgraded the intersection as part of work for Uungula Wind Farm.