Uungula Wind Farm, NSW

Uungula Wind Farm is located on Wiradjuri Country, 14km east of Wellington, NSW. Once complete, the 69-turbine wind farm will generate enough electricity to power more than 220,000 homes and prevent more than 560,000 tonnes of carbon emissions being released into the atmosphere annually.

Key Project Info

Wind turbines

69 x GE 6MW

Maximum capacity

414MW

Status

Under construction

PPA partners

Snowy Hydro

220k+
560k
262
$41m

Stay up to date on the latest Uungula Wind Farm construction news and updates.

Project Timeline

Step 1/13

Project identification and site selection

Identification and site selection is based on an analysis of opportunities and constraints including (but not limited to): distance to the electricity grid, wind resource and population density of the surrounding community. Our team then undertake a number of site visits and consultation with landowners in the area.

Current Stage
DSCF1273

Step 2/13

Project feasibility and community engagement

Site-specific investigations are undertaken to assess the impacts and opportunities of the project and feedback is sought from the local community.

Current Stage
160m Mast

Step 3/13

Development Application and Environmental Impact Statement

A Development Application is made and an EIS prepared which involves a wide range of studies to address stakeholder feedback received to date and to consider the potential environmental and social impacts of the project.

Current Stage
Pexels pixabay 357514

Step 4/13

Public exhibition and Submissions Report

The EIS is placed on public exhibition through the NSW Department of Planning, Housing and Infrastructure. Interested members of the public are invited to have their say during the exhibition period by way of formal submissions. A Submissions Report is then prepared, which aims to respond to the submissions received.

Current Stage
IMG 80711

Step 5/13

Assessment and development consent

The project documents are assessed by the relevant government authorities. If determined, Development Consent is granted alongside a range of conditions specific to the project.

Current Stage
SQE Office 12 C

Step 6/13

Post approval, contracting and financing

A lead contractor(s) to build the project is appointed and all pre-construction approvals and consents are finalised. During this phase, the lead contractor(s) is provided with a list of local businesses that have registered their interest and capabilities through the project website.

Current Stage
SQE Office 3 C

Step 7/13

Procurement

During this phase our lead contractor(s) seek tenders and engage contractors and suppliers to undertake the scope of the works. Orders are then placed for major components such as the wind turbines.

Current Stage
DSCN6131

Step 8/13

Early works and design

Initial site activities commence, such as minor clearing and provision of access roads along with establishing a site construction compound. Off-site detailed design works commences in parallel.

Current Stage
4 170607 WTG wide

Step 9/13

Major civil works

During this phase of the construction the bulk of the civil works takes place. This includes the construction of new internal access roads, excavation and construction of the turbine foundations, installation of the internal electrical reticulation system, construction of the high voltage substation and main transmission line network.

Current Stage
01 Final foundation pour 2

Step 10/13

Wind turbine erection

This is where the visual aspect of the wind farm starts to emerge, with large cranes lifting the tower sections, nacelle, hub and blades into place.

Current Stage
CWP Crudine Ridge Wind Farm JOW 201125 0131

Step 11/13

Commissioning

In order to export power to the grid, each turbine is required to undergo several performance tests. It is during this stage that you will start to see turbines spinning and ultimately the whole of the wind farm complete.

Current Stage
SWF 03 Sapphire Wind Farm landscape 230724 12

Step 12/13

Operations

The project is operating in accordance with relevant approval conditions and management plans. Compliance with conditions of approval and management plans is monitored as required throughout the life of the project.

Current Stage
CWP Sapphire Wind Farm JOW 201111 7104

Step 13/13

Decommissioning

The design life of the wind turbines will be at least 30 years. At the end of their useful life, the wind turbines and electrical equipment will be either replaced and the wind farm repowered, or the project will be decommissioned, and the site returned to its original use at the expense of the project.

Current Stage
20231113 i Phone Bango Wind Farm 72
I Stock 00 IMG Housing EOI  

Accommodation register

We are compiling a register of local accommodation opportunities that are available, or will become available, during the construction and operation of the wind farm.

Accommodation could be used for short-term stays, for example when environmental studies are being carried out by consultants, and for longer-term stays such as during construction.

Uungula Wind Farm is expected to support up to 250 jobs during construction, as well as 12 ongoing jobs during operations.

Community Consultative Committee

The purpose of a community consultative committee (CCC) is to provide a forum for open discussion.

It is a space for us to speak with representatives from the community, the council and other stakeholders about specific matters relating to the wind project.

The CCC follows the NSW Department of Planning, Industry and Environment’s Community Consultative Committee Guidelines for State Significant Projects. Meeting minutes are provided below.

Uungula’s CCC was re-established in 2018. If you would like to get in touch with your local CCC member, please contact the Independent Chairperson:

Mr Garry West
garrybwest@bigpond.com


Publicly Available Documents

CCC Meeting Minutes


Local contractors and service providers are encouraged to register their interest for supplying goods and services

CWP Sapphire Wind Farm JOW 201111 7108  

About Squadron Energy

Squadron Energy is Australia’s leading renewable energy company that develops, operates and owns renewable energy assets in Australia. We are 100% Australian owned and have 1.1 gigawatts (GW) of renewable energy in operation and 900MW under construction. With proven experience and expertise across the project lifecycle, we work with local communities and our customers to lead the transition to Australia’s clean energy future.

Contact

Project Manager

Malcolm McPhan

Email: uungulawind@squadronenergy.com

Mailing Address

16-18 Maughan Street

Wellington NSW 2820

Complaints and Issues Contact Point:

Tel: 0488820191

Newsletter

Receive the latest Uungula Wind Farm project updates straight to your inbox